After months of delay, Vineyard Wind announced it was given the OK to remove a damaged blade and complete its project south ...
What Vineyard Wind needs to do before turning turbines south of Nantucket back on. The wind farm has been offline since a ...
Vineyard Wind early Wednesday morning revealed that it has been given approval to resume installation of turbine blades after ...
The project is removing some blades and "strengthening other blades as needed to support the safety and operational readiness ...
In a Sept. 27 letter addressed to Vineyard Winds’ chief executive and its director of permitting, the Bureau of Safety and ...
The company's reported Q3 loss fell to $99M, or $0.35/share, from a loss of $185M, or $0.62/share in the year-earlier quarter ...
According to GE Vernova, the turbine blade failure was was caused by a “material or manufacturing deviation” at a factory in ...
Vineyard Wind plans to remove an unspecified number of blades from existing turbines after conducting scans and quality ...
Vineyard Wind plans to remove an unspecified number of blades from existing turbines after conducting scans and quality ...
Offshore turbine manufacturer GE Vernova says it is removing some previously installed Haliade-X turbine blades from the ...
We would be really concerned if in six months (from when negotiations began in July) we weren’t in agreement on some core ...